The project duration, measured in terms of the number of months, is the time during which at least one employee worked in the project. Which of the following pairs of the projects had the same duration?
Started 8 months ago by Shashank in
Explanatory Answer
Project 1 & 2 as well as Project 3 & 4 have the same number of months but in the options we only
have Project 3 & 4.
-