Question :

When they work alone, B needs 25% more time to finish a job than A does. They two finish the job in 13 days in the following manner: A works alone till half the job is done, then A and B work together for four days, and finally B works alone to complete the remaining 5% of the job. In how many days can B alone finish the entire job?

Started 3 days ago by Shashank in

Option C is the correct answer.

Explanatory Answer

Its given that B needs 25% more time than A 
So, if Time taken by A = 4x days, Time taken by B = 5x days 
A does half the work, So A works alone for 2x days --- (1) 
A and B work for 4 days --- (2) 
B works alone for 5x/20= x/4 days --- (3) 
Total working days = 13 
(1) + (2) + (3) = 13 
2x + 4 + x/4 = 13 we get, x = 4 
So, B alone can do the work in 5 × 4 = 20 days 
Hence, the answer is 20 days